Contract time-bar calculator

Pick your form of contract and the event, enter the date, and see every notice deadline with the days left. Free, in your browser; nothing is stored or sent.

For information only. Periods are those of the standard forms as published; your contract and its particular conditions decide, and a deadline that falls on a weekend or holiday is not moved here. Not legal advice.

Why the dates matter

Under FIDIC 2017 a contractor who does not give a Notice of Claim within 28 days of becoming aware of the event loses the claim (Sub-Clause 20.2.1), and the fully detailed claim follows within 84 days (20.2.4). NEC4 bars a compensation event not notified within 8 weeks (61.3). Missing a date by one day can cost the entitlement, so the dates are worth counting from the first day.

Form of contractDeadlinePeriodIf missed
FIDIC 2017 Red Book or Yellow BookNotice of Claim (20.2.1)28 daysTime-barred: the claim lapses
FIDIC 2017 Red Book or Yellow BookFully detailed claim (20.2.4)84 daysThe Notice of Claim lapses
FIDIC 2017 Red Book or Yellow BookEngineer's agreement or determination (3.7.3)42 daysDeemed rejected
FIDIC 1999 Red BookNotice of claim (20.1)28 daysTime-barred
FIDIC 1999 Red BookFully detailed claim (20.1)42 daysClaim at risk; check your contract
NEC4 ECCNotify the compensation event (61.3)8 weeksTime-barred (no change to Prices or dates)
NEC4 ECCProject Manager's reply (61.4)1 weeksSend a reminder; if the PM still does not reply within 2 more weeks, the event is deemed accepted
JCT 2024 Standard Building ContractNotice of delay (2.27.1)ImmediatelyFlagged: give notice now
JCT 2024 Standard Building ContractArchitect/CA decision on the extension of time (2.28.2)12 weeksFlagged on the clock
VOB/B 2016Behinderungsanzeige (delay notice) (§ 6 Abs. 1)ImmediatelyEntitlement at risk
VOB/B 2016Announce the claim for additional payment, before the work starts (§ 2 Abs. 6)Before the work startsEntitlement at risk
VOB/B 2016Final payment (Schlusszahlung) due (§ 16 Abs. 3)30 daysDefault interest may run