Behinderungsanzeige: sample delay notice under VOB/B
On a German VOB/B contract, a contractor who is hindered must notify the employer in writing without delay (§ 6 Abs. 1). Free sample letter in German, as a Word file.
Sample: Behinderungsanzeige under § 6 Abs. 1 VOB/B (Word, in German)
A German delay notice: sender, addressee, project, the nature, start and cause of the hindrance, the work affected, its effect, reservation of claims and enclosures. Fill in the yellow parts.
Free, no sign-up. A sample letter, not legal advice.
What the notice contains
- The nature of the hindrance and since when it exists.
- Its cause, and that it is not within the contractor's responsibility.
- The work affected (LV items, sections) and the effect on progress, as far as it can be seen.
- Reservation of the extension of time (§ 6 Abs. 2 and 4) and of the additional cost (§ 6 Abs. 6 VOB/B, § 642 BGB).
- Photos, a Bautagebuch extract and correspondence as enclosures.
Count other periods with the free time-bar calculator → · Quanto on VOB/B projects →
General information, not legal advice. Your contract and its Particular Conditions decide.