Undated site photos: evidence that proves nothing

Quanto site photos tagged by area and linked to events and activities

The Engineer disputes that the ceiling void was ready for the MEP subcontractor on the date the contractor says. The contractor's site engineer is sure he took photos that day. He scrolls through four thousand images on his phone, then on a colleague's phone, then in a shared folder called "Site pics Oct". He finds a photo of an empty void. It has no date in its name, no location and no note. The Engineer looks at it and asks: which floor, and which day?

What it costs

A photo is only evidence if it can be tied to a time, a place and a fact. Without that, it is a picture. In a dispute over access, sequence or the state of work before a variation, the side with photos it can place on a date and an area is the side that is believed. The other side has a gallery.

Example figures

A claim for disruption to a subcontractor's ceiling works is valued at AED 180,000. The contractor's case rests on proving that the void was ready on a given date and the follow-on trade was not. The photos exist, but none can be placed on a floor and a day with certainty. The Engineer assesses the claim on the records that can be checked, and most of it falls away.

How it is usually handled

Everyone on site takes photos on their own phone. Some are sent to WhatsApp groups, where they are compressed and lose their details. Some are copied to a shared drive months later, renamed or not. A few make it into a monthly report with a caption written from memory.

Nobody links a photo to the daily report, the inspection, the variation or the letter it supports. When the photo is needed, it has to be found, and then explained, by someone who may no longer be on the project.

How Quanto Management handles it

In Quanto Management, photos are recorded as part of the project record, not as a separate pile of files.

  • Photos and videos are tagged by area and linked to site events, programme activities, BOQ lines, variations and letters.
  • Site photos can be found by day, area and trade, linked to the day they were taken.
  • Site events in 14 types, such as pours, deliveries, inspections, weather and delays, carry their photos with them.
  • Claims carry linked site events, photos and letters as evidence.
  • One project log records every action automatically, and changes are logged with who and when.

Quanto works in the browser on phones and tablets, so site teams record events and photos from site, at the time, with nothing to install. Storage is measured by the files each project holds, and each project shows its own usage.

A short checklist

  • Take a wide shot first that shows where you are, then the close-up.
  • Write one line with each photo: area, activity and what it shows.
  • Upload photos the same day, not at month end.
  • Do not rely on messaging groups as the store; compressed copies lose their details.
  • Link key photos to the daily report, inspection or letter they support.
  • Before covering up any work, photograph it and record the date.