The BOQ carries a provisional sum for external signage and another for the owner's specialist kitchen equipment. Late in the job, the owner's representative tells the site team on a walk-round to "go ahead with the signage, same supplier as the show villa". The contractor places the order, installs the signs and includes them in the next payment application. The consultant holds the amount: there is no instruction against the provisional sum.
What it costs
Under most standard forms, a provisional sum is a placeholder in the contract sum. It is spent, in whole or in part, only on the Engineer's instruction, and the contract sum is then adjusted for what was actually instructed. Work done without that instruction may not be valued at all, or only after a long argument. The money has already gone to the supplier; the recovery has not come back.
The BOQ includes a provisional sum of AED 250,000 for signage. The contractor orders AED 310,000 of signs on a verbal request, with no instruction and no agreed price. The certifier holds the full amount until the paperwork is in order, and the AED 60,000 above the provisional sum becomes a separate dispute.
How it is usually handled
Provisional sums sit in the BOQ as single lines and are forgotten until someone needs them. Instructions are given in meetings or by phone. The procurement team collects quotations and places the order, and the commercial team only hears about it when the invoice arrives. At any moment, nobody can say how much of each provisional sum has been instructed, ordered or spent.
The money is small compared with the contract sum, which is exactly why nobody watches it.
How Quanto Management handles it
In Quanto Management, the contract, the instruction, the order and the cost sit in one project, so each provisional sum can be followed from the BOQ line to the money spent.
- The BOQ is set up in named sections, each line with its cost code and scope (by contractor or by owner), so each provisional sum can be its own line with its own cost code.
- Instructions from the Engineer or the owner are recorded and answered by the contractor as no cost, variation or disputed, so a request on site becomes a dated record.
- Variations are priced by item, submitted by the contractor, reviewed by the consultant and approved by the owner, with every step dated and named.
- On Professional and above, a vendor quotation must be attached before an order can be issued, and every order is booked against a cost code.
- Per cost code, the cost report shows contract value, budget, committed, actual and what is still to order.
The revised contract sum is always the original plus approved variations, and Quanto keeps a watch on variations as a share of the contract sum. Spending that goes beyond a provisional sum can then be handled as a variation, with its own approval trail.
A short checklist
- List every provisional sum in the BOQ, with its value, at the start of the job.
- Ask for a written instruction before ordering anything against a provisional sum.
- Confirm any verbal go-ahead in writing the same day, quoting the BOQ item.
- Get the quotation accepted before the order, and keep it with the instruction.
- Track each provisional sum as instructed, ordered and spent, and raise it before it is exceeded.