Expired insurance and trade licences on site

Quanto registers with subcontractor licence and insurance expiry dates

A scaffold board falls from the third floor and injures a labourer working for the facade subcontractor. The injury is minor, but the insurer asks for the subcontractor's policy. The copy in the prequalification file expired seven weeks ago; the renewal was "in process". The trade licence in the same file expired a month before that. Nobody on the project knew.

What it costs

A lapsed policy turns an ordinary incident into a commercial problem. The cost may fall back on the main contractor. The owner or the consultant may stop the subcontractor's work until valid documents are produced, and the main contractor has to explain why an uninsured company was on site at all. An expired trade licence can hold up approvals and payments until it is renewed. And a performance bond or advance payment guarantee that expires before the work is finished gives no security at all.

Example figures

A facade subcontract worth AED 3,200,000 is secured by a 10% performance bond of AED 320,000. The bond expires two months before the facade is complete, and nobody asks for an extension. When the subcontractor runs into financial trouble, the security the contractor was counting on is no longer there.

How it is usually handled

Documents are collected once, at prequalification or when the subcontract is signed, and saved in a folder. Expiry dates go into an Excel sheet, if they are written down at all. Nobody is given the job of checking it each month, and the sheet warns nobody. On a project with twenty or thirty subcontractors and suppliers, each with a licence, one or two policies and perhaps a bond, something expires every few weeks.

The documents were valid on the day they were checked. The trouble is that nobody checks again.

How Quanto Management handles it

In Quanto Management (Professional and above), the subcontractor register keeps each company's licence and insurance expiry dates.

  • An expiring insurance policy is flagged before it lapses, not discovered after an incident on site.
  • Guarantees and bonds are recorded with expiry alerts.
  • Work orders carry their payment terms and retention with its release date, so the commercial terms sit with the company they belong to.
  • Vendor payments are released after approval, which gives a natural point to confirm that documents are still valid.

Subcontractors can be invited to the project, and they join free. They work on their own part, such as their submittals and the items waiting on them, while the contractor's costs, margins and other suppliers stay private.

A short checklist

  • Do not let a subcontractor start work until you hold a valid trade licence and insurance certificate.
  • Record the expiry date of every licence, policy and bond, not just the document.
  • Ask in writing for each renewal a month before expiry.
  • Check that the insured amounts and the named insured match what the subcontract requires.
  • Make valid documents a condition of releasing each payment.
  • Compare bond expiry dates with the expected completion date, and ask for extensions when the programme slips.